More details on the new camp nou

More details on the new Camp Nou

More details on the new Camp Nou

Published:3/02/2014 - 17:12h

Updated:

Calendar of FC Barcelona

The capacity of the new Camp Nou would be of 105.053 viewers, the inner construction of the Stadium would happen of 40.000 m² to 104.000 m² and would be finalised in 2021, as it has explained Jordi Moix. The works would begin in summer of 2017

In the press conference of presentation of the new space Barça, the director of the Area Patrimonial, Jordi Moix, has contributed more data of one of the key elements of the project: the construction of a new Camp Nou keeping the structure of the current (ENEA) that it will be subjected to referendum by part of the partners the 5 or on 6 April. It enciphers in 420 million euros. "Once approved, if have very bounded and defined the project will avoid possible deviations of costs", manifested. 

It treats of a very ambitious project, that resume in two data: at present the inner construction of the Camp Nou occupies 40.000 m² , a figure that elevates until the 104.000 m² after all the works. To start with, Moix has explained some concepts of the physical distribution general of the new stadium, that would have an exact capacity for 105.053 viewers

The Camp Nou would follow consisting of three terracings. The first (inferior) would be reformed integralmente, more vertical and with a better visibility. The second would keep , this yes, increasing the comfort. In the third (upper) would complete the ring by the west end (grandstand). 

Fruit of these modifications, the seats would enjoy of more width and comfort, the corridors of access would occupy 1,20 metres of minimum width, all the capacity would be covered, there would be a ring perimetral with vertical services of circulation and would consolidate levelled and orderly plants. The project ENEA also includes a growth of 5.000 squares of parking, as well as diverse improvements in commercial and operative provision. 

Some compatible works with the sportive activity 

On the other hand, Jordi Moix has schematised the phases of the construction of the new Camp Nou and has done an estimate of the calendar. The works will be set up in the summer of 2017, with the demolish of the first terracings of the Goals North and South. In all the process (three seasons and average), the first team of football would follow playing in the Camp Nou and the affectation of the capacity would be minimum. 

And it is that, according to Moix , to minimise the annoyances to the credited, the construction will do by phases and by zones: the terracings during the summers, and the interiors and the outsides during the season of football. It calculates that they would last until March of 2021. The director has left clear that treated of an estimate in function of the plan of urbanismo and licences.

Next match of FC Barcelona

La Liga | Jornada 30
FC Barcelona
Las Palmas

FC Barcelona - Las Palmas

Saturday, 30 of March of 2024 21:00h
Estadi Olímpic Lluís Companys
Buy tickets
Calendar FC Barcelona
Today highlights

Most read